RAL installation: sealing in three levels

The joint between window and wall must be airtight inside, insulated in the middle and rain-proof outside — while still letting moisture in the joint escape. That is what the RAL installation guidelines require, and that is how we install.

  • Tighter inside than outside
  • No thermal bridges
  • No draughts or mould
  • Good practice and EN 14351-1
Section of the window-to-wall joint with three sealing levels: inner tape, insulation and outer vapour-permeable tape123outsideinside

The three-level principle

Three levels, three jobs

The basic rule: tighter inside than outside. Moisture from the room must not get into the joint, and any moisture that does must be able to escape outwards.

1 · Inner level

An airtight, vapour-tight tape stops warm, humid room air from entering the joint and condensing there.

2 · Middle level

Thermal and acoustic insulation (PU foam or mineral wool) fills the joint and prevents thermal bridges.

3 · Outer level

A watertight but vapour-permeable tape keeps out rain and wind while letting moisture from the joint escape.

  1. Inner airtight tape
  2. Joint insulation
  3. Outer vapour-permeable tape

Schematic drawing, not to scale.

Why not just foam

Why foam-only installation fails over time

PU foam onlyThree-level installation
Room moistureEnters the foam and condensesStopped by the inner tape
Rain and UV lightBreak down unprotected foam outsideOuter tape protects the insulation
Insulation over timeWet foam loses its insulating valueInsulation stays dry and effective
ResultDraughts, cold reveals, mouldWarm edges, no draughts or mould

How we work

Installation step by step

  1. Measuring and preparation

    We measure the opening precisely and plan the joint for the wall type and facade insulation.

  2. Fixing

    The window is fixed with screws or anchors and packers so loads are transferred to the wall correctly.

  3. Three-level sealing

    We fit the inner tape, fill the joint with insulation and close it with the outer vapour-permeable tape.

  4. Check and handover

    We adjust the hardware, check operation and sealing, and leave the room clean.

Warranty and standards

Installation you can rely on

We install according to the RAL guidelines for window and door installation and good trade practice; our products comply with EN 14351-1. Warranty terms for products and installation are stated in your quote and warranty certificate.

  • Installed by our own team
  • Removal and disposal of old windows
  • Finishing of reveals on request
Buyer’s guide & energy renovation

Enquiry & quote

Request a made-to-measure quote

Tell us what you are planning. We come to measure on site, advise you on profiles, glazing and colours, and prepare a quote for your building.

  • On-site measuring
  • Advice on systems, glazing and colours
  • A quote prepared for your building